DCMA 14 check-points guarantee many benefits for the project schedule. Some of
those are the following:
- Provide the possibility for a constant in-depth analysis of the schedule;
- Help to identify weak points in the schedule;
- Assist in designating potential problems around the project activities and in
creating appropriate corrective plans;
- Assure that the project is managed and executed with success and on time.
The metrics that need to be followed and examined are the following:
ü Logic
ü Leads
ü Lags
ü Relationship Types
ü Hard Constraints
ü High Float
ü Negative Float
ü High Duration
ü Invalid Dates
ü Resources
ü Missed Tasks
ü Critical Path Test
ü Critical Path Length Index (CPLI)
ü Baseline Execution Index (BEI)
Logic
The metric ‘Logic’ provides the possibility for measurement of the ‘%’ of incomplete
tasks with no predecessors and/or successors, also called ‘dangling’ activities
Lead s
‘Leads’ is the control criteria that helps measure the ‘%’ of tasks that have a
negative lag between each other
Lags
The metric ‘Lags’ is the opposite of ‘Leads’. Specifically, it allows an evaluation of
the ‘%’ of project activities that have a positive lag between each other
Relationship Types
It is recommended that the 90% of the project schedule activities are of a finish-to-
start type (FS). The finish-to-start type of relationship stands for ‘Activity A must be
completed before activity B can begin’. This type of relationship between particular
tasks is the foundation of the Waterfall method used in project management.
Finish-to-start relationship provides the most explicit presentation of the project
schedule activities. The other types of relationships, which can be identified in a
schedule, are finish-to-finish (FF), start-to-start (SS), and start-to-finish (SF).
However, it is not recommendable for these to be used since they are harder to
monitor and control.
Hard Constraints
Under ‘Constraints’ in a project schedule are identified Hard Constraints
(Mandatory Start and Mandatory Finish) and Soft Constraints (As Late As Possible,
Start On, Start On or Before, Start On or After, Finish On, Finish On or Before and
Finish On or After).
High Float
This metric measures the ‘%’ of unfinished tasks with total float greater than 44
working days. DCMA requires that the High Float activity doesn’t exceed 44 working
days, i.e. the percentage of total incomplete tasks doesn’t exceed 5%.
Negative Float
This metric is interconnected with Hard Constraints since it can indicate that Hard
Constraints have been assigned to the schedule. When this happens, it is very much
feasible that the project's or milestones' completion is delayed.
High Duration
This metric provides the possibility to monitor and control the duration of tasks and
it requires that no task should last longer than 44 working days. If it is detected that
the percentage of incomplete tasks with duration beyond 44 days is above 5% it is
preferable to examine if it is achievable to decompose them in distinct tasks.
Invalid Dates
The metric for Invalid Dates analyses both forecast and actual dates of project
activities. An activity is considered to have invalid dates if it has forecast start/finish
dates in the past or actual start/finish dates in the future. More specifically, this
metric refers to tasks with actual start/finish date after project status date and with
start/finish date before project status date without an actual start/finish.
Resources
The metric for ‘Resources’ is the most open-ended on the list. DCMA recommends
that all project schedules are resource-loaded, but additionally, it allows some
schedules to not include resources at all.
Missed Tasks
The metric for ‘Missed Tasks’ can cause or prevent the project to fall far behind. It
assists in measuring the schedule performance in parallel to the baseline plan.
Particularly, the number of missing tasks can indicate how well or badly the project
schedule meets the baseline schedule.
Critical Path Test
This test focusses on assessing the integrity of the schedule’s network logic. Firstly
it is identified as a critical activity and its remaining duration. The next step is
intentionally extending the duration of this activity for 600 days. The last step is
recalculating the schedule dates and identifying if the date for completion of the
project is extended for the same number of days applied to the critical activity.
Critical Path Length Index (CPLI)
The Critical Path Length Index (CPLI) presents the measure of the efficiency
necessary for completing a milestone on assigned time. CPLI evaluates the integrity
of the overall network logic and measures the ‘realism’ of completing a project
successfully.
Baseline Execution Index (BEI)
The Baseline Execution Index (BEI) test is a metric for evaluating schedule
performance in parallel with the baseline plan but it focuses on the project’s team
productivity in the process of executing activities.